|
Under the provisions of
Ontario’s Nutrient Management Act, 2002, Regulation, agricultural
operations generating 300 or more nutrient units annually must be managed in
accordance with a nutrient management strategy including a nutrient
management plan and registered manure spreading agreements. However, the
Regulation excludes from the requirement for a nutrient management strategy
agricultural facilities which were the subject of a building permit
application before September 30, 2003. Where such facilities generate 300 or
more nutrient units annually, must these agricultural operations
nevertheless comply with the nutrient management strategy requirements of
the regulation?
The Ontario Superior Court
recently considered an appeal by municipal residents of the issue of a
building permit for construction of a barn and manure storage silo for an
intensive hog operation which will generate 300 or more nutrient units
annually but for which the building permit application pre-dated September
30, 2003. The court was required to determine whether despite the
application date, the nutrient management strategy requirements of the
Regulation were nevertheless legal requirements with which the proposed
agricultural operation had to comply.
The owner of the proposed
hog operation raised by way of preliminary objection the status of municipal
residents to attack his building permit. In deciding that the appellants had
sufficient interest, the court stated:
“The appellants are
residents and taxpayers in the (municipality). They are neighbours to the
respondent, (owner of the hog operation). All of the appellants,
apparently, draw their water from wells. Given the location of this hog
operation, near the watershed, and a potential environmental damage,
either from leakage of the liquid manure storage tanks or the spreading of
the manure in the area, the concern of the neighbours is justified. The
Court can also appreciate that the neighbours would be concerned about the
smell that emanates from one of these operations and the impact that this
may have on the evaluation of their properties. Finally, the neighbours
have concern about the safety of the roads and bridges, which they use and
lead to (the owner’s) hog operation.”
Even though the building
permit application pre-dated September 30, 2003, the court determined that
issue of the building permit should have been conditional on compliance with
the nutrient management strategy requirements of the Regulation. The court
held:
“As far back as October
2002, the (chief building official) was alive to the issue that such a
large hog operation would generate materials and that these should be
disposed in accordance with a Nutrient Management Plan and
Manure-Spreading Agreement. One would then conclude that, when the go
ahead was given to (the owner), in April or May 2004, the (chief building
official) would certainly have been aware of the provisions of (the
Regulation). He would have been aware that the Nutrient Management Plan
and the Manure Spreading Agreements of (the owner) would have had to
conform with the Nutrient Management Act, 2002. Would it not have
been wise for the (chief building official), when he allowed the
construction of (the owner’s) hog operation to proceed, to have imposed a
condition that (the owner’s) hog operation would not commence until the
provisions of the Nutrient Management Act, 2002 had been complied
with?
Accordingly, I would
order that the respondent, (owner), is not to commence his hog operation,
until he is able to satisfy the requirements of (the Regulation) to the
Nutrient Management Act, 2002”.
Agricultural operations
must comply with the nutrient management strategy requirements of the
Nutrient Management Act if they generate 300 or more nutrient units
annually even if the building permit application for agricultural facilities
pre-dated September 30, 2003. Regardless of the date of building permit
application, such facilities must have a nutrient management plan and
registered manure spreading agreements. |